一个用来计算EAC的常用办法是采用BAC:A.除以SPIB.上SPIC.乘上CPID.除以CPI
一个用来计算EAC的常用办法是采用BAC:
A.除以SPI
B.上SPI
C.乘上CPI
D.除以CPI
一个用来计算EAC的常用办法是采用BAC:
A.除以SPI
B.上SPI
C.乘上CPI
D.除以CPI
20 percent of the work was completed in a project. At this stage, the project manager determined that the budget at completion (BAC) was no longer viable and developed a forecasted estimate at completion (EAC). What index can the project manager use to look at the calculated projection of cost performance that must be achieved on the remaining work。
A.计划绩效指数 (SPI)
A.Schedule Performance Index (SPI)
B.成本绩效指数 (CPI)
B.Cost Performance Index (CPI)
C.成本差异(CV)
C.Cost Variance (CV)
D.完工尚需绩效指数 (TCPI)
D.To-Complete Performance Index (TCPI)。
A.EAC=BAC/CPI
B.EAC=AC+(BAC-EV)
C.EAC=AC+自下而上的ETC
D.EAC=AC+【(BAC-EV)/(CPIxSPI)】
A.16.7%, 60 000
B.20%,60 000
C.16.7%,52 000
D.20%,52 000
A.除以进度绩效指数(SPI)
B.乘以进度绩效指数(SPI)
C.乘以成本绩效指数(CPI)
D.除以成本绩效指数(CPI)
A.管理层认为BAC已明显不可行
B.项目成本超支比较严重
C.项目进度落后比较严重
D.项目必须在规定的时间完工
A.管理层认为BAC已明显不可行
B.项目成本超支比较严重
C.项目进度落后比较严重
D.项目必须在规定的时间完工
A.$250000
B.$220000
C.$280000
D.$200000