You are working on an 18-month project with a small, co-located team . The project sponsor
A.During project executing, you do not need to hold status meetings as long as you send the key stakeholders status report every week .
B.Once a month the entire team, including senior management, should meet with the customer . You should discuss the previous month's issues and the current status .
C.During project execution, it is only necessary for the project manager to meet with the customer once a month to fulfill your contractual obligation . Provide the customer with the status report and copy this report to key stakeholders .
D.The frequency and level of meeting as well as the format and type of information to be exchanged should be defined in the project's communications plan during planning .