The term deflection has a number of meanings, but in terms of pure risk mitigation strate
A.Performing contingent plans
B.Contracting to a sub-contractor
C.Allowing the owner to perform the mitigation strategy since the contractor feels it was not called for in the contract
D.Allowing the float in the schedule to take care of the risk