You are working on an 18-month project with a small, co-located team . The project sponsor
and senior management are in another city and have requested weekly updates . The customer requires monthly meetings . Because the team members are busy with the pr
A.During project executing, you do not need to hold status meetings as long as you send the key stakeholders status report every week .
B.Once a month the entire team, including senior management, should meet with the customer . You should discuss the previous month's issues and the current status .
C.During project execution, it is only necessary for the project manager to meet with the customer once a month to fulfill your contractual obligation . Provide the customer with the status report and copy this report to key stakeholders .
D.The frequency and level of meeting as well as the format and type of information to be exchanged should be defined in the project's communications plan during planning .